VISN 2 Canandaigua - Civil SIte Plan
Updated
A PDF document (431 KB) attached to VISN 2 EHRM Industry Day, from the Department of Veterans Affairs. Due Nov 12, 2026, 2:00 PM (UTC-5).
File name: VISN 2 Canandaigua - Civil SIte Plan.pdf
The full file is for paid members, or buy this bid alone.
Preview
ENCLOSED WALKWAY
M
EA
ST
INLET PROTECTION (TYP.)
(SEE DETAIL 1 ON CS8003)
UP
HEAVY DUTY STORAGE
AREA (SEE NOTE 8)
1 1 4.0
0'
30.
00'
D
.
'
UP
"SIDEWALK CLOSED" SIGN
MOUNTED ON FENCE
(SEE DETAIL 10 ON CS8003)
CONSTRUCTION FENCE
(SEE DETAIL 7 ON CS8003)
EXISTING
BUILDING 37
0'
.0
AM
LIGHT DUTY STORAGE AREA (SEE NOTE 8)
B
BUILDING 100
PROPOSED
DATA CENTER
50.
CONSTRUCTION/STAGING
AREA #2
(SEE NOTE 1)
STE
PRELIMINARY STAGING AREA, EXISTING
CONDITIONS TO BE VERIFIED AND FINAL
STAGING AREA TO BE DETERMINED
CONSTRUCTION FENCE TO BE
LOCATED A MINIMUM OF 5 FT
FROM FACE OF CURB (TYP.)
00'
0'
.
A
DOUBLE SWING GATE,
12 FT WIDE
20 FT WIDE CONSTRUCTION
ENTRANCE (SEE NOTE 10 & 11)
ENCLOSED WALKWAY
TREE PROTECTION FENCE (TYP.)
(SEE DETAIL 4 ON CS8003)
A
TRAILER
D
B
110.00
'
12 FT WIDE DOUBLE SWING GATE
APPROXIMATE LOCATION OF
SHALLOW STEAM TUNNEL
(SEE NOTE 8)
BLD
CONSTRUCTION FENCE
(SEE DETAIL 7 ON CS8003)
D
OA
PR
LOO
G
D
L
B
G
STABILIZED CONSTRUCTION ENTRANCE
(SEE DETAIL 8 ON CS8003)
EXISTING
BUILDING 8
CW
JERSEY BARRIER (TYP.)
(SEE DETAIL 6 ON CS8003)
PEDESTRIAN ACCESS TO BE
MAINTAINED DURING CONSTRUCTION
(SEE NOTES 10 & 11)
3 ACCESSIBLE PARKING SPACES TO BE
BARRICADED FROM USAGE DURING
CONSTRUCTION (SEE NOTE 10)
C
"SIDEWALK CLOSED" SIGN
MOUNTED ON FENCE
(SEE DETAIL 10 ON CS8003)
"NO PARKING ANYTIME" CONSTRUCTION
ENTRANCE SIGN TO BE MOUNTED ON
CONSTRUCTION FENCE (SEE DETAIL 11 ON CS8003)
SAFETY SIGN
(SEE DETAIL 12 ON CS8003)
CONSTRUCTION SIGN
(SEE DETAIL 13 ON CS8003)
1' = 20'
20'
40'
NOTES
D
1.
6/14/2009 12:39:03 PM
G
LD
4.
G
D
L
B 0
5.
6.
CONSTRUCTION/STAGING
AREA #1
EXISTING TELECOM
DUCT BANKS
TO REMAIN
B
u:\Accounts\AEWLA\aewla22044 - canandaigua ny va ehrm upgrades\DESIGN\_SHEETS\AEWLA22044 - G100.dwg
2.
EXISTING CHILLED
WATER LINES
TO REMAIN
E
F
G
3.
G
BLD
7.
G
BLD
8.
MATERIALS TO BE INSTALLED IN THE UPCOMING 48 HOURS MAY BE STAGED IN
CONSTRUCTION/STAGING AREA #1, THE MAJORITY OF THE CONSTRUCTION MATERIALS ARE TO
BE LOCATED IN CONSTRUCTION/STAGING AREA #2.
PROPOSED LEGEND
TELECOM MANHOLE
LIMIT OF DISTURBANCE
DRAINAGE/STORM MANHOLE
BUILDING AREA
CONSTRUCTION ACTIVITIES SHALL BE PERFORMED DURING NORMAL WORKING HOURS (MON. FRI. 8:00am - 4:30pm, EXCLUDING FEDERAL HOLIDAYS) UNLESS INDICATED OTHERWISE IN THE CONTRACT DOCUMENTS OR AS FOLLOWS.
SANITARY SEWER MANHOLE
CERTAIN ACTIVITIES SUCH AS UTILITY SHUT DOWNS, RIGGING OF EQUIPMENT TO THE ROOF, NOISE VIBRATION GENERATING ACTIVITIES (INCLUDING DEMOLITION DRILLING FOR AN ANCHOR INSTALLATION, ETC.) WILL BE COORDINATED WITH THE COR AND WILL HAVE TO BE DONE DURING