MATERIAL LEGEND

PLAN & SECTION

EL8

A
EL1

EL8

EL15

EL3
EL8

SECTION

EXISTING

EARTH

NEW CONSTRUCTION

GRAVEL / FILL

BRICK

METAL

BATT INSULATION

MORTAR NET

CMU

SOLID SURFACE

A

EL1

CONCRETE

EL8

EL11

EL15

GYPSUM BOARD

EL3

EL1

EL15
EL2

EL1

+/- 20'-0"(EXISTING)

EL2

EL7

EL2

+/- 2

EL2

+/- 20'-0"( EXISTING)

EL2

EL2

EL16
EL5

EL5

ELEVATION

PLYWOOD

BRICK

RIGID INSULATION

CMU

SPRAY FOAM

CONCRETE

STONE

WOOD - HORIZONTAL

FIRE PROOFING

WOOD - VERTICAL

EXISTING STUCCO

STUCCO

NOTE: NOT ALL SYMBOLS MAY BE USED ON EACH PLAN

8"
EL5

EL9

8"

4"

EL5

B

ELEVATION KEYED NOTES

EL6

8"
EL1

PROVIDE TAPERED MISSION STYLE CLAY ROOF TILES AND ASSOCIATED

ACCESORIES

EL2

5" ROUND METAL GUTTER, IN-KIND WITH EXISTING, TYP

EL3

PROVIDE METAL PIPE FLASHING AT ALL EXISTING PIPE ROOF

PENETRATIONS

EL4

REINSTALL EXISTING SPLASHBLOCKS REMOVED DURING DEMOLTION

EL5

3" ROUND METAL DOWNSPOUT, TYP

EL6

REINSTALL ALL EXISTING HANDRAILS AND BRACKETS SALVAGED DURING

DEMOLITION IN SAME LOCATION AS EXISTING AFTER REFINISHING

EL7

REINSTALL FABRIC AWNING ASSEMBLY SALVAGED DURING DEMOLITION

EL8

NEW 3-COAT DIRECT APPLIED STUCCO FINISH, CRICKET, AND METAL

FLASHING, ALL SIDES OF EXISTING CHIMNEY

EL9

EXISTING PRECAST CONCRETE CAP TO REMAIN

EL10

INSTALL 7/8" THICK 3-COAT DIRECT APPLIED STUCCO ON WALL AND

ENTRANCE CANOPY IN IT'S ENTIRETY, SEE FLOOR PLAN

EL11

EXISTING PIPE, REINSTALL ONCE STUCCO AND PAINT WORK IS COMPLETE

IF REMOVED TO COMPLETE REFINISHING WORK

EL12

EXISTING MECH AND ELEC SYSTEMS IN THIS AREA, REINSTALL ONCE

STUCCO AND PAINT WORK IS COMPLETE IF REMOVED TO COMPLETE

REFINISHING WORK

EL13

LIGHT FIXTURE, INSTALL IN SAME LOCATION AS DEMOLISHED EXISTING

FIXTURE - SEE ELECTRICAL

EL14

EXISTING CRAWLSPACE VENT TO REMAIN

EL15

METAL SURFACE-MOUNTED COUNTERFLASHING MECHANICALLY

ANCHORED TO CHIMNEY FACE W/ TERMINATION BAR AND BASE FLASHING

BELOW

EL16

REINSTALL SIGN AS DIRECTED BY THE VA COR

EL17

CREDENTIAL READER MOUNT WITH CENTERLINE AT 3'-0" ABOVE FINISHED

FLOOR - SEE TECHNOLOGY

EL18

CIP CONCRETE EQUIPMENT PADS, COORDINATE EXACT LOCATION WITH

THE VA DURING SHOP DRAWING REVIEW – SEE CIVIL AND MECHANICAL

+/- 7'-0"

EL10

+/- 3'-2"

FIRST LEVEL

100'-0"

EL5

EL5

EL4

EL12

EL18

TYP AT ALL

DOWNSPOUTS

EL14

EL5

STUCCO

REPLACEMENT

EL10

TYP AT ALL

DOWNSPOUTS

STUCCO REPLACEMENT

EL4

EL5

EXTERIOR ELEVATION - NORTH

1/4" = 1'-0"

2'

4'

EXTERIOR ELEVATION - EAST

8'

1/4" = 1'-0"

2'

4'

8'

C

EL8

EL15

EL12

EL3

EL3

EL2

EL15

EL8
EL1

EL11

EL1

EL5

EL11

EL1

EL15

EL2

EL2

NOTE: NOT ALL KEYED NOTES MAY BE USED ON EACH ELEVATION

+/- 21'-6" (EXISTING)

OVERALL BUILDING DIMENSION

+/- 20'-0" (EXISTING)