Preview
RENOVATE H8
LABORATORY, B3
TECHNICAL SPECIFICATIONS
VOL. 1
For
AIR FORCE RESEARCH LABORATORY
ROME RESEARCH SITE
ROME, NEW YORK 13441
PROJECT NUMBER: ULDF 200308AE
Prepared By
TOWNE ENGINEERING, P.C.
CONSULTING ENGINEERS
18 South Street
Utica, New York
315.733.9000
May 4, 2026
SECTION
TITLE
01 11 00
Summary of Work
01 14 00
Work Restrictions
01 30 00
Administrative Requirements
01 32 16
Project Schedule
01 33 00
Submittal Procedures
01 35 26
Safety Requirements
01 42 00
Sources for References Publications
01 45 00
Quality Control
01 45 35
Special Inspections
01 50 00
Temporary Facilities
01 57 19
Temporary Environmental Controls
01 74 19
Construction Waste Management and Disposal
01 78 00
Closeout Submittals
01 78 23
Operation and Maintenance Data
02 41 00
Demolition and Deconstruction
03 30 00
Cast-In-Place Concrete
04 20 00
Unit Masonry
05 12 00
Structural Steel
05 30 00
Steel Decks
05 40 00
Cold-Formed Metal Framing
06 10 00
Rough Carpentry
07 21 13
Board and Block Insulation
07 21 16
Mineral Fiber Blanket Insulation
07 53 23
Ethylene-Propylene-Diene Monomer Roofing
07 60 00
Flashing and Sheet Metal
GENERAL REQUIREMENTS TOC - 1
SECTION
TITLE
07 84 00
Firestopping
07 92 00
Joint Sealants
08 11 13
Steel Doors and Frames
08 11 19
Stainless Steel Doors
08 16 13
Aluminum Flush Doors
08 31 00
Access Doors and Panels
08 71 00
Door Hardware
08 81 00
Glazing
09 22 00
Supports for Plaster and Gypsum Board
09 29 00
Gypsum Board
09 51 00
Acoustical Ceilings
09 65 00
Resilient Flooring
09 69 13
Rigid Grid Access Flooring
09 90 00
Paints and Coatings
10 44 16
Fire Extinguishers
13 21 13
Walkable Ceiling System
21 13 13
Wet Pipe Sprinkler Systems, Fire Protection
22 00 00
Plumbing, General Purpose
23 05 15
Common Piping for HVAC
23 05 93
Testing, Adjusting, and Balancing for HVAC
23 09 00
Instrumentation and Control for HVAC
23 09 93
Sequences of Operation for HVAC Control
23 30 00
HVAC Air Distribution
23 51 70
Electric Duct Heaters
GENERAL REQUIREMENTS TOC - 2
SECTION
TITLE
23 51 79
Unit Heaters
23 52 70
Humidifiers
23 53 30
Central Station Heating, Ventilating and Air Conditioning Units, Interior
23 53 70
Power Roof Ventilators, Centrifugal
23 53 82
Laboratory Exhaust Fans
23 55 92
Adjustable Frequency Controllers
26 51 00
Interior Lighting
26 05 19.00 10
Insulated Wire and Cable
26 05 48
Seismic Protection for Electrical Equipment
26 08 00
Apparatus Inspection and Testing
26 20 00
Interior Distribution System
26 29 23
Adjustable Speed Drive (ASD) Systems Under 600 Volts
26 33 53
Static Uninterruptible Power Supply (UPS)
26 41 00
Lightening Protection System
27 10 00
Building Telecommunications Cabling System
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Attachment 3: Suite H8 Specifications Book Vol 2
- Attachment 4: B3 Lighting Floor Plan
- Attachment 5: AFRL Statement of Work-Performance Work Statement Supplemental Requirements (Construction)
- Attachment 6: Price Schedule
- Solicitation - Sep 3
- Bid document
- Bid document
- Plumbing General Purpose
- Bid document
- Bid document
- Metal Wall Panels
- Attachment 9: Submission Complete Set Addendum 1