REHABILITATE CLIMBING FACILITIES AT CAMP MUIR
TITLE II DESIGN DEVELOPMENT AND CONSTRUCTION DOCUMENTS SERVICES
MOUNT RAINIER NATIONAL PARK, PIERCE COUNTY, WASHINGTON
100% CONSTRUCTION DOCUMENTS REPORT
PMIS # 307228
DECEMBER 03, 2025
REHABILITATE CLIMBING FACILITIES AT CAMP MUIR
100% CONSTRUCTION DOCUMENTS REPORT
ECI
12.03.2025
140P8525F0011
REHABILITATE CLIMBING FACILITIES AT CAMP MUIR
100% CONSTRUCTION DOCUMENTS REPORT
OVERVIEW
TEAM
EXECUTIVE SUMMARY
DESIGN NARRATIVES
CODES
EXISTING CONDITIONS & SITE PHASING
CULTURAL RESOURCE COORDINATION
PROGRAM
ARCHITECTURAL
GEOTECHNICAL & CIVIL
STRUCTURAL
ELECTRICAL
HAZMAT ASSUMPTIONS
APPENDIX
APPENDIX A: PROJECT SCHEDULE
SEPARATE DOCUMENTS ISSUED WITH REPORT
100% DESIGN DEVELOPMENT DRAWINGS
100% DESIGN DEVELOPMENT SPECIFICATIONS
100% DESIGN DEVELOPMENT PRODUCT CUT SHEETS
100% DESIGN DEVELOPMENT COST ESTIMATE
ECI
12.03.2025
140P8525F0011
REHABILITATE CLIMBING FACILITIES AT CAMP MUIR
100% CONSTRUCTION DOCUMENTS REPORT
REHABILITATE CLIMBING FACILITIES AT CAMP MUIR
TITLE II DESIGN DEVELOPMENT AND CONSTRUCTION DOCUMENTS SERVICES
MOUNT RAINIER NATIONAL PARK, PIERCE COUNTY, WASHINGTON
100% CONSTRUCTION DOCUMENTS REPORT
PMIS # 307228
CONSULTANT PARTICIPANTS
Jason Swift, Architect and Project Manager, ECI
Brian Meissner, Architect and Value Analysis Facilitator, ECI Emily Hess, Astrid Meissner and Monica Sullivan, Architectural Designers, ECI Nathan Harris, Civil Engineer, PND
Sean Baginski, Structural Engineer, PND
Torsten Mayrberger, Geotechnical Engineer, PND
John Lackey, Electrical Engineer, AMC
Jon Bayles, Estimator, JMB
NPS STAKEHOLDER PARTICIPANTS
Colby Mackley: COR
Greg Dudgeon: Superintendent
Josh Boisvert: Concessions Manager
Kevin Skerl: Deputy Superintendent
Mike Hansen: Rainier Aviation Park Manager (acting)
Stefan Lofgren: Climbing Ranger
Stephanie Clarkson: Historic Architect
Teri Tucker: Planning and Compliance
ECI
12.03.2025
140P8525F0011
REHABILITATE CLIMBING FACILITIES AT CAMP MUIR
100% CONSTRUCTION DOCUMENTS REPORT
ECI
12.03.2025
140P8525F0011
REHABILITATE CLIMBING FACILITIES AT CAMP MUIR
100% CONSTRUCTION DOCUMENTS REPORT
EXECUTIVE SUMMARY
Title II Design Services for the Camp Muir Climbing Shelters is based on design criteria developed during Title I services. These included the Schematic Design Report (dated January 19, 2024, by DJ&A) and the Supplemental Design & Value Analysis Report (dated December 31, 2024, by ECI). The Value Analysis Workshop focused on evaluating construction methods for replacement shelters at Camp Muir in Mount
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Attachment 11: Request for Information Responses
- Attachment 13: Camp Muir Environmental Commitments 1
- Attachment 14: Camp Muir - Gabion Memo
- Attachment 15 2026 Quarry Survey Summary
- Attachment 16: Specificaton Comments
- Attachment 1: Specifications
- Attachment 2: Drawings
- Attachment 3: Product Cut Sheets
- Attachment 5: Wage Determination 5 18 26
- Attachment 8: Past Performance Questionnaire
- Attachment 9: Site Visit Transcript
- Sol