Attachment 61: Contract Data Requirements List TS08 Facility Wiring Design Criteria
Updated
A PDF document (118 KB) attached to TOTAL ENGINEERING AND INTEGRATION SERVICES (TEIS) IV On-Ramp Opportunity, from the Department of the Army. Due Oct 30, 2026, 4:00 PM (UTC-6).
File name: ATT0061 CDRL TS08 Facility Wiring Design Criteria (FWDC).pdf
The full file is for paid members, or buy this bid alone.
Preview
CONTRACT DATA REQUIREMENTS LIST
Form Approved
OMB No. 0704-0188
(1 Data Item)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
D. SYSTEM/ITEM
1. DATA ITEM NO.
TS08
E. CONTRACT/PR NO.
X
F. CONTRACTOR
2. TITLE OF DATA ITEM
17. PRICE GROUP
3. SUBTITLE
Facility Wiring Design Criteria (FWDC)
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
7. DD 250 REQ
N/A
8. APP CODE
N/A
9. DIST STATEMENT
REQUIRED
Required
10. FREQUENCY
12. DATE OF FIRST SUBMISSION
Monthly
18. ESTIMATED
TOTAL PRICE
6. REQUIRING OFFICE
Sample Task 3 para 3.3
USAISEC
14.
DISTRIBUTION
See blk 16
b. COPIES
13. DATE OF SUBSEQUENT
SUBMISSION
11. AS OF DATE
a. ADDRESSEE
16. REMARKS
Final
Draft
See blk 16
Reg
Repro
COR
General. The Facility Wiring Design Criteria (FWDC) provides the A&E designer with TM
specific information required to develop the initial facility lay-out and plans with respect to KO C4I/IT requirements. It specifies, in accordance with applicable standards and regulations, communication equipment placement, signal/cable runs and pathways, power and grounding requirements, C4I/IT interface, and facility penetration points. The FWDC specifically addresses design requirements for Data Center, conference rooms and Command Center Areas. The FWDC is typically included as an Information Technology (IT) annex to the USACE Request for Proposal (RFP) for prospective bidders to use in their design of the C4I/IT building infrastructure.
1. Dates of submission: First Draft 90 calendar days after initial SDP delivery. Second draft 45 calendar days after first draft. Final 45 calendar days after third draft. The government
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Attachment 1: TEIS IV Revised Performance Work Statement
- Attachment 2.5 item a CO 2-2023 USAISEC OPSEC Plan
- Attachment 3 2.5 item b 24-004 USAISEC Drafting Guide
- Attachment 4 2.5 item c 18-033 USAISEC VIS Software Design Criteria
- Attachment 5 2.5 item d SIPRNET Tech Impl Criteria V7
- Attachment 6 2.5 item e 13-033-1 Instructional Guide for Developing EIPs
- Attachment 7 2.5 item i UFC 4-140-03
- Attachment 8 2.5 item j I3A Technical Criteria (for OSP Only) - Copy
- Attachment 9 2.5 item n DISN-EN ICAN-DI Standards Specifications v1 09f
- Attachment 10 2.5 item f USAISEC Cyber Security Assessment and Security Engineering Manual V2.1
- Attachment 13: Contract Data Requirements List A003
- Attachment 24 1.6.1B ESS Network Diagram