SECTION 23 08 00
COMMISSIONING OF HVAC SYSTEMS
1.0
GENERAL
1.1
SUBMITTALS
Government approval is required for submittals. The following shall be submitted in accordance with Section 01 33 00, SUBMITTAL
PROCEDURES:
SD-01 Data
Commissioning Team.
List of team members who will represent the Contractor in the precommissioning checks and functional performance testing, at least 2 weeks prior to the start of pre-commissioning checks. Proposed revision to the list, prior to the start of the impacted work. SD-06 Instructions
Test Procedures
Detailed procedures for pre-commissioning checks and functional performance tests, at least 4 weeks prior to the start of precommissioning checks. SD-07 Schedules
Test Schedule
Schedule for pre-commissioning checks and functional performance tests, at least 2 weeks prior to the start of pre-commissioning checks.
SD-09 Reports
Test Reports
Completed pre-commissioning checklists and functional performance test checklists organized by system and by subsystem and submitted as one package. The results of failed tests shall be included along with a description of the corrective action taken.
April 2019
SECTION 23 08 00
Tinker AFB, OK
1.2
TAFB Technical Specifications 2019
SEQUENCING AND SCHEDULING
The work described in this Section shall begin only after all work required in related Sections, including Section 23 73 33, HEATING,
VENTILATING, AND AIR CONDITIONING (HVAC) CONTROL SYSTEMS and Section
23 05 93, TESTING, ADJUSTING AND BALANCING OF HVAC SYSTEMS, has been
successfully completed, and all test and inspection reports and operation and maintenance manuals required in these Sections have been submitted and approved. Seismic details shall be in accordance
with Sections 13 48 00, SEISMIC PROTECTION FOR MISCELLANEOUS
EQUIPMENT and 22 05 48, SEISMIC PROTECTION FOR MECHANICAL EQUIPMENT
as indicated
1.3
PRODUCTS
3.0
EXECUTION
(NOT APPLICABLE)
3.1 COMMISSIONING TEAM AND CHECKLISTS
The Contractor shall designate team members to participate in the pre-commissioning checks and the functional performance testing specified herein. In addition, the Government will be represented by a representative of the Contracting Officer, the Design Agent's Representative, and the Using Agency. The team members shall be as follows:
Designation
Q
M
E
T
C
D
O
U
Function
Contractor's Chief Quality Control
Representative
Contractor's Mechanical Representative
Contractor's Electrical Representative
The beginning of the document. Download the full file to read on.