DAFF 813 # 327733
REQUEST FOR ENVIRONMENTAL IMPACT ANALYSIS
INSTRUCTIONS:
Section I to be completed by Proponent; Sections II and III to be completed by Environmental Planning Function. Section IV available as continuation space. Add separate sheets as necessary and reference appropriate item number(s).
SECTION I. PROPONENT INFORMATION
1. TO (Environmental Planning Function)
2. FROM (Proponent Organization and functional address symbol)
2a. TELEPHONE NO.
GS-11 Jonathan Garner
78 CEG/CENMP
AFMC/A4C
468-7409
3. TITLE OF PROPOSED ACTION
Address stormwater drainage flume on southeast side of Robins AFB flightline, Facility 8700 4. PURPOSE AND NEED FOR ACTION (Problem Statement: Define the problem that needs a solution & outline goals that meet the solution.)
a. Identify the Proposed Action (Break out into concise discussion). (see attached)
b. State the purpose of this action.
(see attached)
c. State the need for this action.
(see attached)
5. DESCRIPTION OF ACTION AND ALTERNATIVES (DOPAA) (Provide sufficient details for evaluation of the total action. Example questions to consider: What other alternatives have been considered (include the no action alternative)? What alternatives were eliminated from consideration and why? Within this scope of the proposal, is there a construction action and what is its timing? What is the project location (Attach map(s)/diagram(s)) showing project area)? What are additional project requirements, for example, construction and site preparation (include approx. area of ground to be disturbed); laydown yard or storage area resulting in groundwork required; soil borings/sampling/potholing during the design phase (separate dig permit will be required); detailed operational activities; and equipment/material list. Will the project require utilities and if so, how will those utilities be provided to the facility? Any additional details related to the Description of the Proposed Action and Alternatives.
(see attached)
6. PROPONENT APPROVAL (Name and Grade)
6a. SIGNATURE
DEREK A GRIMSLEY, P.E. / NH03
Derek A. Grimsley
Digitally signed by
GRIMSLEY.DEREK.ANTHONY.1591143170
Date: 2026.06.16 09:52:28 -04'00'
6b. DATE
SECTION II – PRELIMINARY ENVIRONMENTAL SURVEY (Check appropriate box and describe potential environmental
+
affects including cumulative effects) (+=positive effect; 0=no effect; - = adverse effect; U=unknown effect)
16 Jun 2026
-
X
1. AIR INSTALLATION COMPATIBLE USE ZONE/LAND USE (Noise, accident potential, encroachment, etc.)
The beginning of the document. Download the full file to read on.
Other documents in this bid
- A.4.2.3 – PAVEMENT CONDITION (7-COLOR PCI RATING)
- DAF PFAS Soil BMPs Playbook
- Day 2 6 PFAS Construction and Best Management Practices
- ESPCP Template v14
- Drainage - Storm Drain Facility 8700 - Specifications
- ONLY UFGS 03 30 00 -Div 1- aphalt and concrete paving
- Submittal Register
- Bid Schedule (Blank)
- Statement of Objectives for PAVE OTA