PIP-II Pipe Support Analysis and Design Deliverable PO
Updated
A PDF document (4.2 MB) attached to Pip-Ii F-37 Building LWC Pump Room Piping System Installation, from the Department of Energy. Due Nov 19, 2026, 2:00 PM (UTC-6).
File name: PIP-II Pipe Support Analysis and Design Deliverable PO 683434.pdf
The full file is for paid members, or buy this bid alone.
Preview
October 20, 2022
Maurice Ball
AD/Mechanical Support Department
Fermilab
Re:
Professional A/E Services for Pipe Support Analysis and Design in support of the Proton Improvement Plan-II (PIP-II) Project
Dear Mr. Ball:
This letter serves as notification of the summary of services provided and transmittal of final deliverables associated with the PO No. 683434.
SERVICES PROVIDED
Burns and McDonnell has completed the following tasks to accomplish this work: 1.
2.
Meetings: Kickoff, In-Progress Reviews, and Final Closeout F37:
a. Reviewed F37 structure for locations and loads from LCW process equipment and piping. b. Updated structural calculations of current building steel to verify capacity. c. See attached Attachment 01, documenting this structural analysis.
3.
CPB
a.
b.
c.
d.
e.
f.
g.
Reviewed structure of CPB for locations and loads from PCW piping. Update structural calculations of current installed building steel to verify capacity. See attached Attachment 01, documenting this structural analysis. Drawings to modify existing structural steel to support PCW loads, will be incorporated in the Utility Plant Building CF Construction Package.
Tabletop review of piping system with manual thermal expansion calculations. i. Note: A floating system with expansion joints at all equipment is sufficient. Please see attached Attachment 02 for a summary of expected thermal expansion and associated calculations.
Provided a drawing (Attachment 03) and specification (Attachment 04) showing the pipe supports / hangers for use by FRA in the PCW work package.
Additional Services: Calculated expected thermal expansion of PCW piping across the bridge as well as within the Linac Gallery, modifications, as necessary will be incorporated into the Linac Complex CF Construction Package (including anchoring of the PCW system to the bridge).
QUALITY CONTROL
This work was performed in accordance with our project-specific QA/QC plan: Q1 – Peer review of key preliminary project activities. Performed by Bart Noland. Q3 – Self-Check of design and construction documents by lead designer. Performed by Ray Weaver, supported by Aidan Chamberlain.
Q4 – Peer review of final submittals Performed by Bart Noland
1431 Opus Place \ Suite 400 \ Downers Grove, IL 60515
O 630-724-3200 \ F 630-724-3201 \ burnsmcd.com
Sincerely,
BURNS & MCDONNELL ENGINEERING COMPANY, INC.
Ray Weaver, PE
Mechanical Engineer / Project Manager
Attachments:
01 Structural Design Review
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Bid document
- Exhibit 10 ESH Requirements
- Exhibit 11 Submittals
- Exhibit 12 Quality Requirements
- Exhibit 13 CESHC
- Exhibit 16 2025 Construction Insurance Requirements
- Exhibit 18 Injury Illness Questionaire
- Exhibit 19 General Decision Number 05 18 2026
- Exhibit 20 SF1413-23a
- Exhibit 21 Bid Bond
- Exhibit 22 Payment Bond
- Exhibit 23 Performance Bond