PIP-II Pump Room Concrete Pad Specification
Updated
A PDF document (56 KB) attached to Pip-Ii F-37 Building LWC Pump Room Piping System Installation, from the Department of Energy. Due Nov 19, 2026, 2:00 PM (UTC-6).
File name: PIP-II F37 Pump Room Concrete Pad Specification.pdf
The full file is for paid members, or buy this bid alone.
Preview
PIP-II F37 Pump Room
FOUNDATIONS, BASES, AND SUPPORTS
A.
B.
Basic Requirements:
1.
Furnish and install foundations, bases, and supports (not specifically indicated on the Drawings or in the Specifications of either the General Construction or Mechanical work as provided by another subcontractor) for mechanical equipment.
2.
All concrete foundations, bases and supports, shall be reinforced. All steel bases and supports shall receive a prime coat of zinc chromate or red metal primer. After completion of work, give steel supports a final coat of gray enamel.
Concrete Bases (Housekeeping Pads):
1.
Unless shown otherwise on the drawings, concrete bases shall be nominal 4 inches thick and shall extend 3 inches on all sides of the equipment (6 inches larger than factory base).
2.
Where a base is less than 12 inches from a wall, extend the base to the wall to prevent a “dirt-trap”.
3.
Concrete materials and workmanship required for the subcontractor's work shall be provided by him. Materials and workmanship shall conform to the applicable standards of the Portland Cement Association. Reinforce with 6”x6”, W1.4-W1.4 welded wire fabric. Concrete shall withstand 3,000 pounds compression per square inch at 28 days.
4.
Equipment requiring bases is as follows:
a.
Centrifugal Pumps
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Bid document
- Exhibit 10 ESH Requirements
- Exhibit 11 Submittals
- Exhibit 12 Quality Requirements
- Exhibit 13 CESHC
- Exhibit 16 2025 Construction Insurance Requirements
- Exhibit 18 Injury Illness Questionaire
- Exhibit 19 General Decision Number 05 18 2026
- Exhibit 20 SF1413-23a
- Exhibit 21 Bid Bond
- Exhibit 22 Payment Bond
- Exhibit 23 Performance Bond