AE-150
22'-11"
1.
INSTALL NEW CERAMIC TILE WAINSCOTING.
2.
INSTALL NEW PLUMBING FIXTURES. SEE MECHANICAL. & ELECTRICAL
1969 ADDITION (NOT HISTORIC)
32'-8"
13'-4"
RENOVATION NOTES:
DRAWINGS.
8'-0"
3.
EXTINGUISHER CABINET. CONTRACTOR TO CHECK FIRE EXTINGUISHER FOR
OPERABILITY. RECHARGE OR REPLACE WITH SIMILAR. ENSURE BOTH
2'-6"
3'-4"
CABINET AND EXTINGUISHER ARE UP TO CODE.
7'-6"
A
NEW M.O.
4.
CONCRETE SLAB BASE.
STORM WINDOW MOUNTING DETAIL
6 NOT TO SCALE
3'-0"
A4
BENCH
GENERAL NOTES
1.
16'-3"
7'-8"
4.
D
B
D
B
C
2" 3'-0"
B
C
5.
5'-8"
A
2'-6"
BENCH
3.
A
A4
2.
AE-150
6.
7.
8.
9.
AE-150
FLOOR PLAN
PROVIDE AND INSTALL NEW METAL LOCKERS
6.
PROVIDE AND INSTALL NEW EYE WASH STATION AND MAT
7.
NEW DOWNSPOUT TO NEW SPLASH BLOCK. SEE CIVIL AND PLUMBING
1 1/4" = 1'-0"
ALL WORK SHALL BE CONDUCTED IN ACCORDANCE
WITH THE SECRETARY OF INTERIOR STANDARDS FOR
HISTORIC PRESERVATION.
PAINT ALL INTERIOR WALLS, CEILINGS, DOORS AND
FRAMES.
INSTALL NEW EXTERIOR METAL DOOR FRAMES AND
DOORS.
REINSTALL ALL HISTORIC WOOD WINDOWS, DOORS
AND FRAMES AND INSTALL NEW EXTERIOR STORM
WINDOWS WITH SCREENS DESIGNED TO PRESERVE
HISTORICAL ELEMENTS.
REMOVE, REHABILITATE AND REINSTALL HISTORIC 3
SLIDING WOOD BARN DOORS, STEEL WINDOW AND
DOOR LINTELS, AND DOOR FRAMES.
CLEAN, PATCH AND PREPARE ALL INTERIOR WALLS,
CEILINGS, DOORS AND FRAMES.
REMOVE ALL EXTERIOR STEEL DOOR FRAMES AND
DOORS.
REMOVE AND REHABILITATE ALL HISTORIC WOOD
WINDOWS, DOORS AND FRAMES .
REMOVE, REHABILITATE AND REINSTALL HISTORIC
SLIDING WOOD BARN DOORS, STEEL WINDOW AND
DOOR LINTELS, AND DOOR FRAMES
10. SEE AE-116 FOR PARTITION TYPES.
DRAWINGS.
8.
PROVIDE NEW EPOXY FLOORING, SEE STRUCTURAL DRAWINGS FOR
DETAILS.
9.
PROVIDE NEW COPPER PLUMBING PLUMBING TO WATER FOUNTAINS AND
HAND SINK WITH SURFACE MOUNTED COPPER SUPPORT.
10. REHABILITATE AND REINSTALL EXISTING CHIMNEY CROWN, FASCIA, AND
SOFFIT.
12. PROVIDE AND INSTALL NEW ASPHALT SHINGLE ROOF, METAL DRIP EDGE,
B
AE-150
5.
11'-0"
REPLACE EXISTING WATER HEATER. RELOCATE TO MECHANICAL CLOSET ON
A
13'-412"
AND FLASHING
13. PROVIDE AND INSTALL NEW 6" HALF-ROUND COPPER-COLORED GUTTERS
AND DOWNSPOUTS.
14. REROUTE EXISTING LINES UNDERGROUND.
15. FINISH EXPOSED CONDUIT SHERWIN WILLIAMS "CLASSICAL WHITE".
NOTES
DO NOT REMOVE PULLEY. LEAVE IN PLACE.
REMOVE, REHABILITATE AND REINSTALL
CHIMNEY CROWN
C
TYP
Sim
A-501
5"
D
8'-3"
16'-10"
3'-4"
NEW M.O.
MEN'S LOCKER ROOM SIGN
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Jessamine Camp Nelson Building
- Jessamine Camp Nelson Heavy
- Jessamine Camp Nelson Highway
- From CNNC FCA Corrections CONS BD DRAWINGS VOL 1
- From CNNC FCA Corrections CONS BD DRAWINGS VOL 1
- From CNNC FCA Corrections CONS BD DRAWINGS VOL 1
- From CNNC FCA Corrections CONS BD DRAWINGS VOL 1
- From CNNC FCA Corrections CONS BD DRAWINGS VOL 1
- From CNNC FCA Corrections CONS BD DRAWINGS VOL 1
- From CNNC FCA Corrections CONS BD DRAWINGS VOL 1
- From CNNC FCA Corrections CONS BD DRAWINGS VOL 1
- From CNNC FCA Corrections CONS BD DRAWINGS VOL 1