LEGEND

LIMITS OF LIMESTONE REMOVAL

UW

EXISTING GRADE CONTOUR

UW

NEW GRADE CONTOUR

D

UW

UW

GRAVESITE MONUMENT

1.5"

U
UWW

UW

4" UNDERDRAIN AND CLEANOUT

3"

UW

A

EX. IRRIGATION

D

UW

KEYNOTES

UW

A

W

UW

D

UW

UW

D

UW

REMOVE TOPSOIL, FILL, AND HARDENED

IDENTIFICATION LAYER. EXPOSE CRYPT LIDS

CLEANED OF ALL SOIL FOR INSPECTION. CONSTRUCT

IDENTIFICATION LAYER, BACKFILL, AND TOPSOIL.

CG-201

PROTECT EXISTING UNDERDRAIN CLEANOUTS, PIPES,

UW

02 GRAVESITE MONUMENTS, AND IRRIGATION.

UW

1.5"

D

UW

1.25"

NOTES

2"

UW

20D

D

UW

D

D

D

1.

MATCH EXISTING FINISH GRADING OF BURIAL SECTION C-C.

CONTOURS SHOWN ARE APPROXIMATE, FOR GENERAL

INFORMATION ONLY.

2.

MINIMIZE LANDSCAPE DISRUPTION. MATS SHALL BE USED TO

PROTECT GROUNDS ON VEHICLE ACCESS ROUTES.

3.

PRIOR TO CONSTRUCTION, SUBMIT CRYPT FIELD EXCAVATION PLAN.

INCLUDE EQUIPMENT, EXCAVATION TECHNIQUE, COMPACTION

TECHNIQUE, VEHICLE CIRCULATION, MAT LAYOUT, HAUL ROUTE, SEQUENCE, ANTICIPATED SCHEDULE, AND PERSONNEL ASSIGNED.

4.

RIGID CONSTRUCTION MATS ARE REQUIRED FOR ALL WHEELED

VEHICLE TRAFFIC OVER CRYPT FIELD. TRACKED VEHICLES AND

MATS UNDER LOAD SHALL EXERT A MAXIMUM 200 PSF PRESSURE

ON GROUND. MAXIMUM WHEELED VEHICLE AXLE WEIGHT IS

12,000 LBS (6,000 LB WHEEL LOAD).

5.

CONTRACTOR SHALL PROTECT PPC FIELDS FROM VEHICLE OR

MATERIAL OVERLOADING. WARNING SIGNAGE AND/OR

TEMPORARY FENCING TO KEEP HEAVY VEHICLES 10-YARDS AWAY

FROM EDGE OF CRYPT FIELDS SHOULD BE USED. SPOILS AND

BACKFILL PILES HAVE THE SAME EFFECT AS HEAVY VEHICLES; AND

SHALL ALSO BE KEPT 10-YARDS AWAY FROM EDGE OF CRYPT FIELDS.

6.

EMPLOY LAND SURVEYOR LICENSED IN THE STATE OF KENTUCKY TO

SURVEY MONUMENTS, CLEANOUTS, IRRIGATION HEADS, AND ANY

OTHER SURFACE FEATURES WITHIN LIMITS OF CRYPT FIELD.

SUBMIT SEALED SURVEY PRIOR TO CONSTRUCTION. SURVEYOR

SHALL RE-SURVEY AT CONCLUSION OF WORK, AND SUBMIT SEALED

SURVEY.

7.

PROTECT MONUMENTS, CLEANOUTS, AND IRRIGATION HEADS.

REPLACE ANY DAMAGED OR DISPLACED ITEMS AT NO COST TO THE

GOVERNMENT.

8.

PROTECT CRYPTS AND CRYPT LIDS. REPLACE ANY CRYPTS OR

COMPONENTS DAMAGED OR DISPLACED BY CONTRACTOR

OPERATION AT NO COST TO THE GOVERNMENT.

9.

TIGHTLY CONTROL FINISHED BACKFILL DEPTHS AS REQUIRED BY

DETAILS. SURFACE GRADING GENERALLY SHALL MATCH EXISTING

GRADE, BACKFILL DEPTH REQUIREMENTS SHALL CONTROL. PROBE

IN FINISHED BACKFILL DEPTH IN PRESENCE OF COR NO LESS THAN

100 LOCATIONS.

UW

B

2"
D

W

U

1"

W

U

B

D

UW

D

W
U

UW

3"
UW

UW

UW

UW

UW

UW

UW

C

1.25"

SECTION C-C

C

1.25"

D

10. SEQUENCE REMOVAL AND REPLACEMENT OF MATERIAL. NO CRYPT

SHALL BE EXPOSED FOR MORE THAN 7 DAYS. NO BACKFILLED AREA

SHALL REMAIN UNGRASSED FOR MORE THAN 7 DAYS.

The beginning of the document. Download the full file to read on.