Tinker AFB
Tinker General Requirements
SECTION 01 45 00
QUALITY CONTROL
PART 1
1.1
GENERAL
REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C1077
(2024) Standard Practice for Agencies
Testing Concrete and Concrete Aggregates
for Use in Construction and Criteria for
Testing Agency Evaluation
ASTM D3666
(2016) Standard Specification for Minimum
Requirements for Agencies Testing and
Inspecting Road and Paving Materials
ASTM D3740
(2019) Minimum Requirements for Agencies
Engaged in the Testing and/or Inspection
of Soil and Rock as Used in Engineering
Design and Construction
ASTM E90
(2023) Standard Test Method for Laboratory
Measurement of Airborne Sound Transmission
Loss of Building Partitions and Elements
ASTM E329
(2023) Standard Specification for Agencies
Engaged in Construction Inspection,
Testing, or Special Inspection
ASTM E543
(2021) Standard Specification for Agencies
Performing Non-Destructive Testing
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1
(2024) Safety -- Safety and Occupational
Health (SOH) Requirements
ER 1110-3-12
(2021) Military Engineering and Design
Quality Management
U.S. DEPARTMENT OF DEFENSE (DOD)
FC 1-300-09N
1.2
(2024) Navy and Marine Corps Design
PAYMENT
Separate payment will not be made for providing and maintaining an effective Quality Control program. Include all associated costs in the applicable Bid Pricing Schedule item.
October 2026
Section 01 45 00
Tinker AFB
1.3
Tinker General Requirements
SUBMITTALS
Government approval is required for submittals with a "G" classification. Submittals not having a "G" classification are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
SD-01 Preconstruction Submittals
Contractor Quality Control (CQC) Plan; G
Additional Requirements For Design Quality Control (DQC) Plan; G SD-05 Design Data
Design Quality Control
Discipline-Specific Checklists
SD-06 Test Reports
Verification Statement
1.4
GENERAL REQUIREMENTS
Establish and maintain an effective quality control (QC) system that complies with FAR 52.246-12 Inspection of Construction. QC is comprised of plans, procedures, and organization necessary to produce an end product that complies with the Contract requirements. The QC system covers all design and construction operations, both onsite and offsite, and must be
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Contract Data Requirements List - Organization Chart Signed
- Contract Data Requirements List - Quaterly Progress Mtg Signed
- Contract Data Requirements List - TO Progress Mtg Signed
- Appendix A - Abbreviations
- Appendix B1 TAFB General Requirements Div 00-01
- Appendix C UMRL
- Attachment 1: Statement of Work Jun26
- Attachment 2b Appendix B Work Sample Cover Sheet4May26
- Attachment 3: Section M Evaluation Criteria
- TAFB Technical Requirements Div 02-48
- ERDCITL r2
- ERDCITL r6