Tinker AFB

Tinker General Requirements

SECTION 01 45 00

QUALITY CONTROL

PART 1

1.1

GENERAL

REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C1077

(2024) Standard Practice for Agencies
Testing Concrete and Concrete Aggregates
for Use in Construction and Criteria for
Testing Agency Evaluation

ASTM D3666

(2016) Standard Specification for Minimum
Requirements for Agencies Testing and
Inspecting Road and Paving Materials

ASTM D3740

(2019) Minimum Requirements for Agencies
Engaged in the Testing and/or Inspection
of Soil and Rock as Used in Engineering
Design and Construction

ASTM E90

(2023) Standard Test Method for Laboratory
Measurement of Airborne Sound Transmission
Loss of Building Partitions and Elements

ASTM E329

(2023) Standard Specification for Agencies
Engaged in Construction Inspection,
Testing, or Special Inspection

ASTM E543

(2021) Standard Specification for Agencies
Performing Non-Destructive Testing

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1

(2024) Safety -- Safety and Occupational
Health (SOH) Requirements

ER 1110-3-12

(2021) Military Engineering and Design
Quality Management

U.S. DEPARTMENT OF DEFENSE (DOD)

FC 1-300-09N
1.2

(2024) Navy and Marine Corps Design

PAYMENT

Separate payment will not be made for providing and maintaining an effective Quality Control program. Include all associated costs in the applicable Bid Pricing Schedule item.

October 2026

Section 01 45 00

Tinker AFB

1.3

Tinker General Requirements

SUBMITTALS

Government approval is required for submittals with a "G" classification. Submittals not having a "G" classification are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
SD-01 Preconstruction Submittals
Contractor Quality Control (CQC) Plan; G
Additional Requirements For Design Quality Control (DQC) Plan; G SD-05 Design Data
Design Quality Control
Discipline-Specific Checklists
SD-06 Test Reports
Verification Statement
1.4

GENERAL REQUIREMENTS

Establish and maintain an effective quality control (QC) system that complies with FAR 52.246-12 Inspection of Construction. QC is comprised of plans, procedures, and organization necessary to produce an end product that complies with the Contract requirements. The QC system covers all design and construction operations, both onsite and offsite, and must be