UNCLASSIFIED

CONTRACT DATA REQUIREMENTS LIST

A. CONTRACT LINE ITEM NO.

C. CATEGORY:

B. EXHIBIT

TDP

D. SYSTEM/ITEM

1. DATA ITEM NO.

E. CONTRACT/PR NO.

F. CONTRACTOR

2. TITLE OF DATA ITEM

OTHER

TM

3. SUBTITLE

17. PRICE GROUP

Quarterly Progress Meeting

5. CONTRACT REFERENCE

4. AUTHORITY (Data Acquisition Document No.)

Not Applicable

7. DD 250 REQ

No

8. APP CODE

6. REQUIRING OFFICE

MACC SOW, Paragraph 11.11.7

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

N/A

11. AS OF DATE

N/A

18. ESTIMATED

TOTAL PRICE

72 ABW/CEN & AFSC/PZIOC

12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

Block 16
Block 16

b. COPIES

Block 16

13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Final
Draft
Reg

Block 16

AFSC/PZIOC

72 ABW/CEN

The Contractor shall schedule quarterly meetings to discuss status of all awarded Task Orders. The Contractor shall provide an agenda prior to the meeting and prepare minutes of the meeting and distribute to all parties in attendance.

16. REMARKS

Repro

Provide Meeting Agenda and Presentation materials within 5 calendar days of the scheduled meeting. Provide Meeting Minutes within 5 calendar days of the progress meeting. Meeting shall address, at a minimum, the following:
Organizational structure showing key positions and any changes since last meeting List of currently Awarded TOs
- Award date
- Project Manager and Superintendent
- Current vs Planned percentage complete
- Contractual vs. Projected completion date
- (Design Build only) Most recent design milestone and projected date for next - (Design Build only) Scheduled design completion date vs. projected - List of outstanding RFIs
- List of outstanding submittals
- Any issues which may affect completion date
Discussion of issues/challenges for the Basic Contract.

add continuation

G. PREPARED BY

Richard Stewart

DD FORM 1423, FEB 2024

Show Attachment Bar

H. SIGNED ON 20260709

Digitally signed by

STEWART.RICHARD.ALLEN.12698

41741
Date: 2026.07.09 08:22:33 -05'00'

15.TOTAL

I. APPROVED BY

J. SIGNATURE

Ray Green

signed by
GREEN.TIMOTHY Digitally

GREEN.TIMOTHY.RAY.1146518911

.RAY.1146518911 Date: 2026.07.09 08:56:14 -05'00'

UNCLASSIFIED

PREVIOUS EDITION MAY BE USED.

+

-

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoDM 5010.12 for detailed instructions.)

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.
Item B. Self-explanatory.
Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.