Dugway Proving Ground Fugitive Dust Control Plan Form 02 Sand and Gravel Borrow Pit Operations
Screening of Rock, Soil or Construction Debris
Activity Description: The mechanical process which accomplishes a division of particles on the basis of size.
General Information
Location(s):
Start Date:
End Date:
Point of Contact:
Email:
Phone Number:
Description of site:
Fugitive Dust Emission Control Techniques
Select at least one best management practice (BMP) for each critical mitigation area: Stabilize surface soils where support equipment and vehicles will operate BMP 02-01 Pre-water and maintain surface soils in a stabilized condition. BMP 02-02 Apply and maintain a chemical stabilizer to surface soils. (Name of chemical: BMP 02-03 Pave operational area(s).
Pre-treat material prior to screening
BMP 02-04 Apply a dust suppressant to material. (Name of chemical: Stabilize material during screening
BMP 02-05 Dedicate water source to screening operation and apply water as needed to prevent dust. BMP 02-06 Install wind barrier upwind screen as high as the drop point. Stabilize material after screening
BMP 02-07 Apply water to stabilize screened material and surrounding area. Apply and maintain a chemical stabilizer to stabilize screened material and surrounding area. BMP 02-08
(Name of chemical:
BMP 02-09 Minimize storage pile height.
Transfer height
BMP 02-10 Drop material through the screen slowly and minimize drop height.
)
)
)
Logbook Requirement
All screening operations require a logbook be kept, at minimum, it must contain: the date and amount of material screened. If suppression is used, (i.e. water/chemical suppressant), additional logbook entries are required, at minimum, entries must contain: the date, time, type of suppression used, amount (in gallons), purpose and location applied.
Trackout Prevention
In accordance with Utah Administrative Code R307-205-6(2), any person(s) performing fugitive dust emission activities will to the maximum extent possible, keep material from being deposited onto any paved road other than a designated deposit site. Any such person(s) who deposits materials that may create fugitive dust on a paved road shall clean the road promptly. *By signing you attest that you have read and understand the requirements of the DPG FDCP and will follow the BMPs you have selected.
Signature
Date
This form is to be completed and kept on record according to the requirements found in the Dugway Proving Ground (DPG) Fugitive Dust Control Plan
The beginning of the document. Download the full file to read on.
Other documents in this bid
- 1442-Solicitation DPG Horizontal Construction
- Attachment 1: Scope of Work W911S6 Construction Horizontal FY27 - FY 31
- Standard Specification Book Rev
- Paving IDIQ Airfield Specifications
- Materials Manual of Instruction
- Min Sampling an Testing
- Quality Management Plans
- Work Zones
- Dust Control Forms
- TE-09a Fugitive Dust Control Form 01-Crushing
- TE-09c Fugitive Dust Control Form 03-Stockpiles
- TE-09d Fugitive Dust Control Form 04-Hauling