Home / Dugway Proving Ground (DPG) Horizontal Facility… / Document

TE-09q Fugitive Dust Control Form 17-Trackout

Updated

A PDF document (748 KB) attached to Dugway Proving Ground (DPG) Horizontal Facility Construction Road Maintenance, from the Department of the Army. Due Nov 18, 2026, 1:00 PM (UTC-7).

File name: TE-09q Fugitive Dust Control Form 17-Trackout.pdf

Download the full documentSee the bid

The full file is for paid members, or buy this bid alone.

Preview

Dugway Proving Ground Fugitive Dust Control Plan Form 17 Roads, Paved and Unpaved

Trackout Prevention and Cleanup of Mud, Silt and Soil Tracked onto Paved Roads Activity Description: The depositing of mud, silt and soil onto paved roads by vehicles or equipment.

General Information
Location(s):

Start Date:

End Date:

Point of Contact:

Email:

Phone Number:

Description of site:

Fugitive Dust Emission Control Techniques
Select at least one best management practice (BMP) for each critical mitigation area: Prevent dust from trackout
BMP 17-01 Clean trackout at the end of the work shift from paved surfaces to maintain dust control. BMP 17-02 Maintain dust control during working hours and clean trackout from paved surfaces at the end of the work shift/day. Install gravel pad(s), clean, well-graded gravel or crushed rock. Minimum dimensions must be 30 feet wide by 3 inches BMP 17-03 deep, and, at minimum, 50' or the length of the longest haul truck, whichever is greater. Re-screen, wash or apply additional rock in gravel pad to maintain effectiveness. BMP 17-04 Install wheel shakers. Clean wheel shakers on a regular basis to maintain effectiveness. BMP 17-05 Install wheel washers. Maintain wheel washers on a regular basis to maintain effectiveness. BMP 17-06 Motorized vehicles will only operate on paved surfaces. BMP 17-07 Install cattle guard before paved road entrance. All exiting traffic must be routed over selected trackout control device(s) BMP 17-08 Clearly establish and enforce traffic patterns to route traffic over select trackout control device(s). Limit site accessibility to routes with trackout control devices in place by installing effective barriers on unprotected BMP 17-09
routes.

Trackout Prevention

In accordance with Utah Administrative Code R307-205-6(2), any person(s) performing fugitive dust emission activities will to the maximum extent possible, keep material from being deposited onto any paved road other than a designated deposit site. Any such person(s) who deposits materials that may create fugitive dust on a paved road shall clean the road promptly. *By signing you attest that you have read and understand the requirements of the DPG FDCP and will follow the BMPs you have selected.

Signature

Date

This form is to be completed and kept on record according to the requirements found in the Dugway Proving Ground (DPG) Fugitive Dust Control Plan (FDCP). Copies of form(s) shall be provided to EP, Air Program Manager, upon the completion of operation(s) and/or annually at the end of each calendar

The beginning of the document. Download the full file to read on.

Other documents in this bid