TO2A J-11 Scaffolding Sample Task Order 2 Complex Visual Aide

Updated

A PDF document (2.2 MB) attached to LBNF/DUNE-US South Dakota Scaffolding Services, from the Department of Energy. Due Nov 24, 2026, 4:00 PM (UTC-7).

File name: TO2A J-11 Scaffolding Sample Task Order 2_Complex Visual Aide.pdf

Download the full documentSee the bid

The full file is for paid members, or buy this bid alone.

Preview

Locations #1-3
Locations to gain
access to install on
Cavern walls.

Locations #4

Location to install
support system

Locations #1-4

210 Inches – from top of
cryostat to highest location
for pipe hanger install.

81 ½ Inches

Installation
height of
Platform
from top of
cryogenic
beams.

Locations #1-3
Full length walking
platform, that
cantilevers off the
side of the cryostat
to access anchor
points on cavern
wall. However, this
walking platform
will need to be
anchored to the top
of the cryostat.

Locations #1-3

Distance from side
of cryostat to
cavern north wall to
gain access to
anchor points = 1-2
½ ft, due to
changes in the
cavern wall.

Locations #1-3
Cavern Wall (Not Flat)
Distance from side of
cryostat to cavern north
wall to gain access to
anchor points = 1-2 ½
ft, due to changes in the
cavern wall.

The beginning of the document. Download the full file to read on.