Arc Flash Hazard Analyses
Contract No. VA36C24923P0897
Contracting Officer: Lara Hampton
Phone No: (615)225-5414

Veterans Affairs Medical Center
Bowling Division
Lexington, Kentucky

Project Report - Volume 2
November 2023 – February 2024

Submitted by

Jerry M. Parks Jr., Project Manager

William
Henderson
LLC
4041 Greenfern Drive
Lockhart, Florida 32810
(407)427-0436

in cooperation with

305 Wendy Hill Road
Savannah, Georgia 31410
(803)760-3138

Cover

Arc Flash Hazard Analyses
Volume 2
Contract No. VA36C24923P0897

Veterans Affairs Medical Center – Bowling Division
Lexington, Kentucky
November 2023 – February 2024

Section 1

Equipment Data Files (by building)

Arc Flash Hazard Analyses, Contract No. 36C24923P0897
VA Medical Center – Bowling Division – Lexington, Kentucky

Equipment Data Schedules

Enclosed are the data schedules for each piece of equipment evaluated under this arc flash hazard analyses. Data schedules have been grouped by location. Each major group is separated by a red divider page to distinguish the groups.
The groups are categorized as follows:
Main Hospital
▪

Life Safety Bus Duct #1

▪

Life Safety Bus Duct #2

▪

ESB2

▪

ESB3

▪

ESB4

▪

Low Voltage Switchboard Bus #1

▪

Low Voltage Switchboard Bus #2

▪

Normal Power A & B

▪

Normal Power C & D

▪

Medium Voltage Equipment

Tower Building
▪

Generator

▪

Switchboard SBA

▪

Switchboard SBB

▪

Switchboard SBC

▪

Switchboard SBD

▪

Switchboard SBE

▪

Switchboard SBF

▪

Switchboard SBG

▪

Switchboard SBH

▪

Medium Voltage Equipment

Chiller Plant
▪

Low Voltage Switchgear

▪

Medium Voltage Equipment

Cable Schedule
Location:

Main Hospital - LS Bus Duct #1
Power

Location

Source

Load

Equipment Type

Phases

Size
Neutral

Type

Ground

Phases

Qty
Neutral

Ground

Distance

Main Swgr Bus #1

ATS-LS

ATS

250 kCMIL

250 kCMIL

#1 AWG

THHN

50'

ATS-LS

ESB1

Switchboard

250 kCMIL

250 kCMIL

#1 AWG

THHN

25'

ESB1

LS Bus Duct #1

Busway

Busway

LS Bus Duct #1

ELP1C Disconnect

Bus Disconnect

Busway

ELP1C Disconnect

ELP1C

Panel

#2 AWG

#2 AWG

#6 AWG

THHN

10'

ELP1C

T-EPP1C

LV Transformer

#4 AWG

#4 AWG

#6 AWG

THHN

5'

T-EPP1C

EPP1C

Panel

#1 AWG

#1 AWG

#2 AWG

THHN

10'

LS Bus Duct #1

ELP2C Disconnect

Bus Disconnect

Busway

ELP2C Disconnect

ELP2C

Panel

#3 AWG

#3 AWG

#8 AWG

THHN

10'

LS Bus Duct #1

ELP3C Disconnect

Bus Disconnect

Busway

ELP3C Disconnect

ELP3C

Panel

#2 AWG

#2 AWG

#6 AWG

THHN

5'

ELP3C

T-EPP3C

LV Transformer

#8 AWG

#8 AWG

#10 AWG

THHN

5'

T-EPP3C

EPP3C

Panel

#3 AWG

#3 AWG

#6 AWG

THHN

10'

LS Bus Duct #1

T-EPP3D Disconnect

Bus Disconnect

Busway

T-EPP3D Disconnect

T-EPP3D

LV Transformer