Draft B2 03.09 01 Packaging Procedure MV Switchgear Shipping Preparation-2
Updated
A PDF document (3.2 MB) attached to SLAC CUIR SP1 Master Substation Annex Building Construction, from the Department of Energy. Due Oct 27, 2026, 5:00 PM (UTC-7).
File name: DRAFT_B2_03.09_01_Packaging_Procedure_1VAM-T0004-020086_MV_Switchgear_Shipping_Preparation-2.pdf
The full file is for paid members, or buy this bid alone.
Preview
Uncontrolled copy
UNCONTROLLED
Disregard After 06/11/2025
COPY
Document ID Number:
1VAM-T0004-020086
Windchill
d
e
l
l
o
r
Current Revision: 6
Electrification Business
Distribution Solutions
North America
t
n
o
c
Un
y
p
Co
Owner: Production Supervisor
QMS Document Path:
Effective Date: Upon
Windchill Release
Title: MV SWGR Shipping Preparation
Author: Jordan Curington
PROCESS MAP
N/A
AF
T
Approver(s): Quality manager and Operations manager
d
e
l
l
o
r
t
n
o
c
Un
y
p
Co
PURPOSE
R
To provide work instructions for ABB MV Switchgear shipping preparation.
SCOPE/INTRODUCTION
D
This procedure applies to ABB MV Switchgear at the Mebane, NC facility.
RESPONSIBILITY
It is the responsibility of all ABB MV Switchgear assembly personnel to understand and follow this procedure. It is the responsibility of management to ensure assembly personnel are trained on this document and that this document is maintained and updated.
d
e
l
l
o
tr
n
o
c
n
U
y
p
Co
Uncontrolled copy
TOOLS & MATERIALS REQUIRED
d
e
l
l
o
r
t
n
o
c
Un
y
p
Co
Clear Tape
AF
T
Masking Tape (Blue)
d
e
l
l
o
r
R
t
n
o
c
Un
y
p
Co
Cardboard Corners
D
Disregard After 06/11/2025
d
e
l
l
o
tr
n
o
c
n
U
y
p
Co
Strapping
Dispenser
Stretch Wrap
Uncontrolled copy
Disregard After 06/11/2025
SAFETY PRACTICE
Safety glasses, gloves, and steel toe shoes should be used as the standard safety practice. When performing work on top of switchgear, a safety harness should be used. All ladder safety standards must be followed.
d
e
l
l
o
r
t
n
o
c
Un
y
p
Co
PROCEDURE
All switchgear assembly personnel are to follow quality workmanship standards (Document number: 1VAM-T0004-900019) as well as health and safety requirements.
Front and rear door closing
AF
T
After Quality Assurance Team has cleared the section for shipping, close front and rear panels.
d
e
l
l
o
r
R
t
n
o
c
Un
y
p
Co
D
7.1
•
Confirm all latched doors are fully
closed
•
If front doors are bolted style, tighten
all bolts.
d
e
l
l
o
tr
n
o
c
n
U
y
p
Co
Tighten all rear door bolts
Uncontrolled copy
Shipping Member Label Installation
d
e
l
l
o
r
AF
T
t
n
o
c
Un
y
p
Co
d
e
l
l
o
r
R
t
n
o
c
Un
y
p
Co
D
7.2
Disregard After 06/11/2025
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Draft B2 00 Cover Letter
- Draft B2 01 Request for Proposals Section A (Subcontract Form)
- Draft B2 02 Request for Proposals Section B (Supplies or Services and Price Costs
- Draft B2 03.00 Request for Proposals Section C (Specifications Statement of Work)
- Draft B2 03.01 Statement of Work
- Draft B2 03.03 Commissioning Plan
- Draft B2 03.04 CUIR Subproject 1 Power Outages and Linac Downtime Plan
- Draft B2 03.05 CUIR's Quality Requirements for Subcontractors
- Draft B2 03.06 Department of Energy Order 414.1E Quality Assurance
- Draft B2 03.08 00 Appendix I Technical Data Submittal
- Draft B2 03.12 Certified Test Reports SWGR9 SWGR8
- Draft B2 03.13 Certificate of Conformity